Nancy Hill View, Baner
by Sarsan Aawishkar Properties. Baner, Pune 411045. View on Google Maps
- Launched
- First of 3 phases
- Possession dates (MahaRERA)
- Jun 2028 – Dec 2030varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 81%Mid-construction1 of 3 phases with structure completeWeighted across 3 phases
- Units booked
- 87 of 13564% booked
- Price per sq ft
- ₹9,6002026 salesSee what buyers paid
Facts
Project facts
| 1 BHK | 24 |
|---|---|
| 2 BHK | 56 |
| 3 BHK | 55 |
| Total units | 135 |
| Buildings | 3 |
| Land | 1.7 acres |
| Phases | 3 |
Since Dec 2025: booked 79 → 84
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 3 BHK | about 1,330 – 1,370 sq ft | ₹1.23 – 1.31 crore | 2026 sales |
Price per sq ft, year by year
| 2026 | ₹9,600 per sq ft |
|---|
Registered sales across all 3 phases.
Compared with the typical Baner rate in 2026: about 30% lower
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Nancy Hill View A-3 Mid-construction | P52100052211 | 84 | 90% | 100% | |
| Nancy Hill View B 1 Mid-construction | P52100079084 | 27 | 35% | 7% | |
| Nancy Hill View B-2 Ready to move | P52100079837 | 24 | 100% | 4% |
Show updates by phase
Nancy Hill View A-3 (P52100052211)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 84 | |
| 100% | 90% | 0% | 79 | |
| 100% | 90% | 0% | 50 | |
| 100% | 49% | 0% | 45 | |
| 100% | 34% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Nancy Hill View B 1 (P52100079084)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 2 | |
| 100% | 33% | 0% | — | |
| 100% | 22% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Nancy Hill View B-2 (P52100079837)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 1 | |
| 100% | 100% | 100% | — | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 411045
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 11 mths | 4 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2028 – Dec 2030 | March 2028 |
| Concrete structure (RCC) | 81% | 92% |
| Units booked | 64% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Infinito Sereno | July 2023 | December 2028 | 40% | 36 of 120 booked (30%) |
| 5 Maidan by Skyi | May 2023 | June 2028 | 100% | 173 of 191 booked (91%) |
| Dream Glorious | September 2023 | June 2027 | 95% | 63 of 76 booked (83%) |
| 37 Grandstand | September 2023 | May 2027 | 90% | 31 of 64 booked (48%) |
| Portia Grande | April 2023 | December 2027 | 100% | 129 of 132 booked (98%) |
| Dream Elegance | April 2023 | December 2028 | 50% | 129 of 207 booked (62%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
Other phases of this project
About this project
Nancy Hill View is a project by Sarsan Aawishkar Properties in Baner, Pune 411045, registered with MahaRERA as 3 phases (P52100052211, P52100079084, P52100079837). The first phase was launched in July 2023. Together the phases have 135 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from June 2028 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 81% complete and final finishes 18% complete. 1 of the 3 phases have their structure complete.
87 of the 135 units reported for sale are booked (64%). In 2026 registered sales, 80% of flats here sold at ₹9,600 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 30% lower than the typical Baner rate in 2026. Most buyers paid ₹1.23–1.31 crore for 3 BHK flats of about 1,330–1,370 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.