Skip to main content
← Back

Blueroof Sylva, Sus

by SS Properties. Sus, Pune 411021. View on Google Maps

Launched
6 years 1 month promised
Possession date (MahaRERA)
3 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
6%Mid-constructionAverage across 3 buildings
Units booked
58 of 19330% booked
Price per sq ft (incl. balconies and terrace)
₹8,2002026 so far · 14 salesup 5% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK17
2 BHK128
Other units (shops, offices or not given by type)48
Total units193
Buildings3
Land3.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 21 → 58 · structure 0% → 6%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
860 – 870 sq ft₹67 – 69 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹7,800 per sq ft12 sales
2026 so farup 5% on 2025₹8,200 per sq ft14 sales

Rate vs other Sus projects, 2026: similar

Compared with 6 similar projects in PIN 411021

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 1 mth4 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2030March 2029
Concrete structure (RCC) complete6%76%
Share of units booked30%65%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 5 months of the promised 6 years 1 month have passed
Concrete structure (RCC) 6% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 6%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 6%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%0%58
100%0%0%21
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Blueroof Sylva (MahaRERA P52100056053) is a residential project by SS Properties in Sus, Pune 411021. It was launched in May 2024. It has 193 units in 3 buildings: 145 homes (1 & 2 BHK) and 48 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 6% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

58 of its 193 units are booked (30%). Since the December 2025 update, 37 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 6%. 80% of the 2026 (so far) sales we found here were at ₹8,200 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size, based on 14 registered sales. Buyers here paid a rate similar to other Sus projects in 2026. Most buyers paid ₹67–69 lakh for flats of 860–870 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100056053.Check it on MahaRERA (P52100056053)All projects in Bavdhan, Pashan, Sus