Skip to main content
← Back

Ganga Legend B5 Building, Bavdhan Budruk

by Legends County Landmark Pvt Ltd. Bavdhan Budruk, Pune 411021. View on Google Maps

Launched
3 years 6 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
8%Mid-construction
Units booked
143 of 21467% booked
Price per sq ft (incl. balconies and terrace)
₹11,9002026 so far · 23 salesup 7% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK10
3 BHK203
4 BHK1
Total units214
Buildings1
Land1.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 133 → 143 · structure 1% → 8%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,260 – 1,400 sq ft₹1.33 – 1.59 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,200 per sq ft62 sales
2025down 1% on 2024₹11,100 per sq ft74 sales
2026 so farup 7% on 2025₹11,900 per sq ft23 sales

Rate vs other Bavdhan Budruk projects, 2026: about 15% higher

Compared with 6 similar projects in PIN 411021

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 6 mths5 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2027May 2029
Concrete structure (RCC) complete8%48%
Share of units booked67%52%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 4 months of the promised 3 years 6 months have passed
Concrete structure (RCC) 8% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 1%Jul 2026: Concrete structure (RCC) 8%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 8%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%0%143
100%1%0%133
100%0%0%62
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Ganga Legend B5 Building (MahaRERA P52100076756) is a residential project by Legends County Landmark Pvt Ltd in Bavdhan Budruk, Pune 411021. It was launched in June 2024. It has 214 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 8% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

143 of its 214 units are booked (67%). Since the December 2025 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 1% to 8%. 80% of the 2026 (so far) sales we found here were at ₹11,900 per sq ft or less (up 7% on 2025), counting balconies and terrace in the size, based on 23 registered sales. Buyers here paid a rate about 15% higher than at other Bavdhan Budruk projects in 2026. Most buyers paid ₹1.33–1.59 crore for flats of 1,260–1,400 sq ft.

Goel Ganga's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA61
Completed without extending the possession date18
Completed after an extension, or lapsed14
Under construction29
Possession date extended by the builder16
Typical time from launch to 100% structure5 years 1 month
Complaints on MahaRERA, all Goel Ganga projects141 (27 of 61 projects)

See all Goel Ganga projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100076756.Check it on MahaRERA (P52100076756)All projects in Bavdhan, Pashan, Sus