Skip to main content
← Back

Oriana World, Tathawade

by Balaji Builders. Tathawade, Pune 411033. View on Google Maps

Launched
3 years 8 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
18%Mid-constructionAverage across 2 buildings
Units booked
161 of 31551% booked
Price per sq ft (incl. balconies and terrace)
₹10,1002026 so far · 58 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK75
2 BHK190
3 BHK50
Total units315
Buildings2
Land4.4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 43 → 161 · structure 0% → 18% · final finishes 0% → 30%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
730 – 810 sq ft₹65 – 82 lakh
1,150 sq ft₹1.11 – 1.19 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹10,100 per sq ft15 sales
2026 so farabout the same as 2025₹10,100 per sq ft58 sales

Rate vs other Tathawade projects, 2026: similar

Compared with 6 similar projects in PIN 411033

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 8 mths4 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2028February 2030
Concrete structure (RCC) complete18%2%
Share of units booked51%62%
Complaints on MahaRERA (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 6 months of the promised 3 years 8 months have passed
Concrete structure (RCC) 18% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 18%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Excavation 100%Final finishes 30%Concrete structure (RCC) 18%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%30%161
100%0%0%43
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Oriana World (MahaRERA P52100080096) is a residential project by Balaji Builders in Tathawade, Pune 411033. It was launched in April 2025. It has 315 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 18% complete, final finishes 30% complete. MahaRERA records do not show it as ready to move in.

161 of its 315 units are booked (51%). Since the December 2025 update, 118 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 18%. 80% of the 2026 (so far) sales we found here were at ₹10,100 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 58 registered sales. Buyers here paid a rate similar to other Tathawade projects in 2026. Most buyers paid ₹65–82 lakh for flats of 730–810 sq ft and ₹1.11–1.19 crore for 1,150 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100080096.Check it on MahaRERA (P52100080096)All projects in Tathawade, Punawale, Jambhe