Skip to main content
← Back

Life Republic Sector R14/14TH Avenue - Qrious/phase - I, Jambhe

by Kolte-Patil Developers Limited. Jambhe, Pune 411033. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
3 years 6 months awayPossession date unchanged since launch
Concrete structure (RCC)
3%Mid-constructionAverage across 2 buildings
Units booked
344 of 45276% booked
Price per sq ft (incl. balconies and terrace)
₹9,4002026 so far · 67 salesup 2% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK196
3 BHK196
4 BHK8
Other units (shops, offices or not given by type)52
Total units452
Buildings2
Land7.6 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 280 → 344 · structure 0% → 3%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
790 – 890 sq ft₹77 – 86 lakh
1,100 sq ft₹1.02 – 1.06 crore
1,210 sq ft₹1.11 – 1.15 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹9,200 per sq ft263 sales
2026 so farup 2% on 2025₹9,400 per sq ft67 sales

Rate vs other Jambhe projects, 2026: similar

Compared with 6 similar projects in PIN 411033

Projects with 200–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 1 mth3 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)April 2030February 2029
Concrete structure (RCC) complete3%10%
Share of units booked76%60%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 3% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 0%Dec 2025: Excavation 85%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 3%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 3%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%3%0%344
85%0%0%280
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Life Republic Sector R14/14TH Avenue - Qrious/phase - I (MahaRERA P52100079623) is a residential project by Kolte-Patil Developers Limited in Jambhe, Pune 411033. It was launched in March 2025. It has 452 units in 2 buildings: 400 homes (2, 3 & 4 BHK) and 52 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2030, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 3% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

344 of its 452 units are booked (76%). Since the December 2025 update, 64 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 3%. 80% of the 2026 (so far) sales we found here were at ₹9,400 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size, based on 67 registered sales. Buyers here paid a rate similar to other Jambhe projects in 2026. Most buyers paid ₹77–86 lakh for flats of 790–890 sq ft, ₹1.02–1.06 crore for 1,100 sq ft and ₹1.11–1.15 crore for 1,210 sq ft.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079623.Check it on MahaRERA (P52100079623)All projects in Tathawade, Punawale, Jambhe