Kiran Swastik Building B, Sus

by Kiran Creators and Developers Private Limited. Sus, Pune 411021. View on Google Maps

Launched
2 years 8 months originally promised
Possession date (MahaRERA)
2 years awayExtended by 1 year 5 months (originally May 2027). Why possession dates change
Concrete structure (RCC)
4%Mid-construction
Units booked
57 of 22525% booked
Price per sq ft (incl. balconies and terrace)
₹8,3002026 so far · 45 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

Total units225
Buildings1
Land0.4 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
730 – 810 sq ft₹61 – 67 lakh
940 sq ft₹74 lakh
1,000 sq ft₹83 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹8,300 per sq ft109 sales
2026 so farabout the same as 2025₹8,300 per sq ft45 sales

Rate vs other Sus projects, 2026: similar

Compared with 4 similar projects in PIN 411021

Projects with 300–1,300 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 8 mths4 yrs 10 mths
Possession date extendedBy 1 year 5 months0 of 4
Possession date (MahaRERA)October 2028July 2029
Concrete structure (RCC) complete4%0%
Share of units booked25%42%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 1 month of the originally promised 2 years 8 months have passed
Concrete structure (RCC) 4% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 4%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Excavation 70%Concrete structure (RCC) 4%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%4%0%57
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kiran Swastik Building B (MahaRERA PC1261012400016) is a residential project by Kiran Creators and Developers Private Limited in Sus, Pune 411021. It was launched in September 2024. It has 225 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2028, extended by 1 year 5 months from the original May 2027. Construction: excavation 70% complete, structure (RCC) 4% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

57 of its 225 units are booked (25%). 80% of the 2026 (so far) sales we found here were at ₹8,300 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 45 registered sales. Buyers here paid a rate similar to other Sus projects in 2026. Most buyers paid ₹61–67 lakh for flats of 730–810 sq ft, ₹74 lakh for 940 sq ft and ₹83 lakh for 1,000 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PC1261012400016.Check it on MahaRERA (PC1261012400016)All projects in Bavdhan, Pashan, Sus