Ace projects in Pune
MahaRERA projects by Ace registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 34 |
|---|---|
| Total units across these projects | 3,769 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 13 |
|---|---|
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 13 |
| Not updated on MahaRERA for over a year | 1 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ace projects | 16 (5 of 34 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
- Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.
Where they build: Mundhwa (3) · Ravet (2) · Kiwale (2) · Charholi Budruk (1) · Balewadi (1) · Rahatani (1) · Lohegaon (1) · Thergaon (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Ace Abode · 5 phases | Kiwale | Ready to move | Dec 2025 – Jun 2027 | 645 units booked out of total 651 units |
| Ace Abundance | Mundhwa | Early stage | March 2030 | 40 units booked out of total 173 units |
| Ace Aster | Kiwale | Early stage | March 2029 | 240 units booked out of total 299 units |
| ACE Atmosphere Phase I | Ravet | Mid-construction | September 2028 | 312 units booked out of total 340 units |
| Ace Ayodhya · 2 phases | Thergaon | Early stage | Dec 2030 – Apr 2032 | 277 units booked out of total 834 units |
| ACE Villas | Mundhwa | Nearing possession | December 2026 | 6 units booked out of total 10 units |
| Jhamtani BizOne | Rahatani | Early stage | December 2030 | 0 units booked out of total 35 units |
| Jhamtani Elevate | Mundhwa | Early stage | December 2028 | 158 units booked out of total 197 units |
| Maitri Meadows | Lohegaon | Early stage | March 2029 | 0 units booked out of total 69 units |
Completed
| Project | Village | Status |
|---|---|---|
| Ace | Dhankawadi | Completed |
| ACE Aastha | Charholi Budruk | Completed |
| Ace Aastha | Moshi | Completed |
| Ace Almighty Commercial | Tathawade | Completed |
| Ace Almighty Gamma | Tathawade | Completed |
| Ace Augusta | Maan | Completed |
| Ace Aurum | Ravet | Completed |
| Auralia Residency | Punawale | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Ace Almighty Delta | Tathawade | Lapsed |
| Nandan ACE | Balewadi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us