Shapoorji projects in Pune

MahaRERA projects by Shapoorji registered 2018–2026 in Pune & PCMC.

Projects registered with MahaRERA59
Total units across these projects10,067
Full record

MahaRERA projects registered 2018–2026 in Pune & PCMC

Completed without extending the possession date26
Completed after an extension1
Lapsed4
Under construction28
Possession date extended on the builder's application5
Typical time from launch to 100% structure3 years
MahaRERA complaints (filed by or against the builder), all Shapoorji projects38 (16 of 59 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Lavale (6) · Shewalewadi (4) · Maan (2)

Under construction

ProjectVillageStagePossessionBooked
EWS Building · 2 phasesShewalewadiMid-constructionMar 2027 – Sep 2027153 units booked out of total 258 units
Golfland · 4 phasesLavaleMid-constructionDec 2028 – Dec 2029499 units booked out of total 543 units
Joyville Celestia · 5 phasesShewalewadiMid-constructionMar 2028 – Sep 2029580 units booked out of total 1,158 units
Joyville Hadapsar Annexe · 14 phasesShewalewadiNearing possessionJun 2025 – Dec 20271,968 units booked out of total 2,010 units
Joyville Hadapsar Sky-LuxeShewalewadiNearing possessionDecember 2026160 units booked out of total 168 units
Sensorium · 7 phasesMaanMid-constructionMay 2025 – Dec 20261,156 units booked out of total 1,291 units
Vanaha Springs T1 WillowLavaleNearing possessionMarch 2027307 units booked out of total 307 units
Vanaha Springs T2 CedarLavaleNearing possessionDecember 2026306 units booked out of total 307 units
Vanaha Springs T3 AspenLavaleNearing possessionDecember 2026355 units booked out of total 367 units
Vanaha Verdant ELM I & IILavaleEarly stageMarch 20322 units booked out of total 240 units
Vanaha Verdant Mahogany I & IILavaleEarly stageJune 2030125 units booked out of total 363 units
Vyomora · 3 phasesMaanEarly stageApr 2031 – Dec 20310 units booked out of total 720 units
Completed
ProjectVillageStatus
EwsShewalewadiCompleted
Joyville Hadapsar AnnexeShewalewadiCompleted
Joyville HinjawadiMaanCompleted
YahaviLavaleCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us