Bliss County, Charholi

by Ganesh Satish Patil. Charholi, Pune 412105. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Dec 2024 – Jun 2027varies by phase1 of 3 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
46%Mid-construction1 of 3 phases with structure completeWeighted across 3 phases
Units booked
92 of 12673% booked · 2 phases not reported
Price per sq ft
₹7,2002026 salesup 9% on 2025See what buyers paid

Project facts

1 BHK187
2 BHK115
Total units343
Buildings4
Land1.5 acres
Phases3
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 450 – 480 sq ft₹29 – 37 lakh2026 sales
2 BHKabout 640 – 690 sq ft₹44 lakh2026 sales

Price per sq ft, year by year

2023₹5,700 per sq ft
2024up 2% on 2023₹5,800 per sq ft
2025up 14% on 2024₹6,600 per sq ft
2026up 9% on 2025₹7,200 per sq ft

Studios (under 450 sq ft): ₹6,600 per sq ft in 2025 sales, up 3% on 2024. Sizes about 440 sq ft.

Registered sales across all 3 phases.

Compared with the typical Charholi rate in 2026: about 25% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Studios are priced separately from flats and are not used in area price comparisons or on the Property rates page.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Bliss County Phase I
Nearing possession
P52100029452126100%73%
Bliss County Phase 2
Mid-construction
P5210005313612610%Not reported
Bliss County Phase 3
Early stage
P52100076734500%Not reported
Show updates by phase

Bliss County Phase I (P52100029452)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%92
100%100%50%36

"—" means MahaRERA shows no figure for that update.

Bliss County Phase 2 (P52100053136)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%—
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Bliss County Phase 3 (P52100076734)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 5 similar projects in PIN 412105

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs5 yrs
Possession date extendedYes1 of 5
Possession date (MahaRERA)Dec 2024 – Jun 2027July 2026
Concrete structure (RCC)46%89%
Units booked73%92%
MahaRERA complaints (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Bliss County is a project by Ganesh Satish Patil in Charholi, Pune 412105, registered with MahaRERA as 3 phases (P52100029452, P52100053136, P52100076734). The first phase was launched in May 2021. Together the phases have 343 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from December 2024 to June 2027; 1 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 46% complete and final finishes 21% complete. 1 of the 3 phases have their structure complete.

92 of the 126 units reported for sale are booked (73%); 2 phases have not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹7,200 per sq ft or less (up 9% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 25% lower than the typical Charholi rate in 2026. Most buyers paid ₹29–37 lakh for 1 RK / 1 BHK flats of about 450–480 sq ft (2026 sales); ₹44 lakh for 2 BHK flats of about 640–690 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra. Its studios (under 450 sq ft) sold at ₹6,600 per sq ft or less in 2025; studios are priced separately from flats.

Source: MahaRERA registrations P52100029452, P52100053136 and P52100076734.Open MahaRERA and search P52100029452All projects in Charholi, Moshi