by Tulip Properties. Moshi, Pune 412105. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
May 20261 of 2 phases have an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
Units booked
278 of 30192% booked

Project facts

1 BHK79
2 BHK266
3 BHK4
Total units349
Buildings2
Land1.6 acres
Phases2

Since Dec 2025: booked 275 → 278

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Infinity Planet B Wing
Completed
P52100030463117100%88%
Infinity Planet E Wing
Ready to move Lapsed
P52100034091232100%75%
Show updates by phase

Infinity Planet B Wing (P52100030463)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%103
100%100%0%99

"—" means MahaRERA shows no figure for that update.

Infinity Planet E Wing (P52100034091)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%175
100%100%60%172
100%67%0%145
100%28%0%101
100%0%0%71

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 412105

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 4 mths5 yrs
Possession date extendedYes2 of 6
Possession date (MahaRERA)May 2026May 2026
Concrete structure (RCC)100%78%
Units booked92%90%
MahaRERA complaints (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Infinity Planet is a project by Tulip Properties in Moshi, Pune 412105, registered with MahaRERA as 2 phases (P52100030463, P52100034091). The first phase was launched in August 2021. Together the phases have 349 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is lapsed.

The registered possession date is May 2026; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 66% complete. 2 of the 2 phases have their structure complete.

278 of the 301 units reported for sale are booked (92%).

Source: MahaRERA registrations P52100030463 and P52100034091.Open MahaRERA and search P52100030463All projects in Charholi, Moshi