Skip to main content
← Back

Godrej Meadows- Phase 2, Baner

by Mahalunge Township Developers Private Limited. Baner, Pune 411045. View on Google Maps

Launched
4 years 1 month originally promised
Possession date (MahaRERA)
2 months awayExtended by 1 year (originally December 2025). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
493 of 49899% booked

Project facts

1 BHK4
2 BHK240
3 BHK244
Other units (shops, offices or not given by type)10
Total units498
Buildings3
Land3 acres
Complaints on MahaRERA (filed by or against the builder)45

Since Dec 2025: final finishes 43% → 86% · complaints 2 → 45

Share on WhatsApp

Compared with 4 similar projects in PIN 411045

Projects with 200–1,000 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 1 mth5 yrs 3 mths
Possession date extendedBy 1 year0 of 4
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete100%90%
Share of units booked99%86%
Complaints on MahaRERA (filed by or against the builder)450

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 67%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 19%Jun 2024: Concrete structure (RCC) 83%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 16%Dec 2024: Final finishes 43%Jun 2025: Final finishes 43%Dec 2025: Final finishes 43%Jul 2026: Final finishes 86%Excavation 100%Concrete structure (RCC) 100%Final finishes 86%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%86%493
100%100%43%493
100%100%43%491
100%83%16%475
67%19%0%441

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Godrej Meadows- Phase 2 (MahaRERA P52100031794) is a residential project by Mahalunge Township Developers Private Limited in Baner, Pune 411045. It was launched in November 2021. It has 498 units in 3 buildings: 488 homes (1, 2 & 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 86% complete. MahaRERA records do not show it as ready to move in.

493 of its 498 units are booked (99%).

Godrej's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date9
Completed after an extension, or lapsed2
Under construction30
Possession date extended by the builder11
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Godrej projects441 (35 of 41 projects)

See all Godrej projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031794.Check it on MahaRERA (P52100031794)All projects in Baner, Balewadi, Mahalunge