Life Canvas, Mamurdi

by Vighnaharta Reality. Mamurdi, Pune 412101. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2025 – Jun 2027varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
91%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
412 of 50881% booked

Project facts

1 BHK184
2 BHK254
3 BHK64
Total units538
Buildings5
Land3 acres
Phases2

Since Dec 2025: booked 376 → 412

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Life Canvas Phase 1
Ready to move Lapsed
P52100032021251100%94%
Life Canvas Phase 2
Mid-construction
P5210005351725182%61%
Show updates by phase

Life Canvas Phase 1 (P52100032021)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%237
100%100%93%237
100%85%25%248
100%68%0%245
100%30%0%173

"—" means MahaRERA shows no figure for that update.

Life Canvas Phase 2 (P52100053517)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%17%175
88%45%0%139
50%10%0%97
33%7%0%43
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 412101

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 6 mths4 yrs 2 mths
Possession date extendedYes3 of 6
Possession date (MahaRERA)Dec 2025 – Jun 2027September 2026
Concrete structure (RCC)91%100%
Units booked81%93%
MahaRERA complaints (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Life Canvas is a project by Vighnaharta Reality in Mamurdi, Pune 412101, registered with MahaRERA as 2 phases (P52100032021, P52100053517). The first phase was launched in December 2021. Together the phases have 538 units in 5 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2025 to June 2027; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 91% complete and final finishes 59% complete. 1 of the 2 phases have their structure complete.

412 of the 508 units reported for sale are booked (81%).

Source: MahaRERA registrations P52100032021 and P52100053517.Open MahaRERA and search P52100032021All projects in Kiwale, Ravet