The Balmoral Hillside, Baner

by Kanika Infracon LLP. Baner, Pune 411045. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2028 – Jun 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
2%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
65 of 17238% booked

Project facts

4 BHK180
5+ BHK2
Total units192
Buildings2
Land0.3 acres
Phases2

Since Dec 2025: booked 112 → 65

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Balmoral Hillside - Tower B , Phase I
Mid-construction
P52100046444568%29%
The Balmoral Hillside-Tower A, Phase II
Early stage
P521000520221260%36%
Show updates by phase

The Balmoral Hillside - Tower B , Phase I (P52100046444)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%0%16
100%8%0%63
100%8%0%74

"—" means MahaRERA shows no figure for that update.

The Balmoral Hillside-Tower A, Phase II (P52100052022)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%49
0%0%0%5

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411045

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 2 mths4 yrs 8 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028 – Jun 2029December 2026
Concrete structure (RCC)2%89%
Units booked38%73%
MahaRERA complaints (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

The Balmoral Hillside is a project by Kanika Infracon LLP in Baner, Pune 411045, registered with MahaRERA as 2 phases (P52100046444, P52100052022). The first phase was launched in July 2022. Together the phases have 192 units in 2 buildings, with 4 & 5+ BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 2% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

65 of the 172 units reported for sale are booked (38%).

Source: MahaRERA registrations P52100046444 and P52100052022.Open MahaRERA and search P52100046444All projects in Baner, Balewadi, Mahalunge