Anika Piccadilly, Punawale

by Arun Pitamber Sheth. Punawale, Pune 411033. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2027 – Dec 2028varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
96%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
285 of 40870% booked
Price per sq ft
₹8,4002026 salesup 9% on 2025See what buyers paid

Project facts

2 BHK396
3 BHK12
Total units408
Buildings2
Land0.4 acres
Phases2

Since Dec 2025: booked 155 → 285

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 800 sq ft₹60 – 67 lakh2026 sales

Price per sq ft, year by year

2023₹7,100 per sq ft
2024up 3% on 2023₹7,300 per sq ft
2025up 5% on 2024₹7,700 per sq ft
2026up 9% on 2025₹8,400 per sq ft

Registered sales across all 2 phases.

Compared with the typical Punawale rate in 2026: about 20% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Anika Piccadilly Phase 2
Nearing possession
P52100049940244100%94%
Anika Piccadilly Phase 3
Mid-construction
P5210007887516490%34%
Show updates by phase

Anika Piccadilly Phase 2 (P52100049940)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%229
100%100%50%144
100%85%10%144
100%60%0%98
100%30%0%30

"—" means MahaRERA shows no figure for that update.

Anika Piccadilly Phase 3 (P52100078875)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%56
100%0%0%11
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411033

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 4 mths3 yrs 9 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027 – Dec 2028May 2027
Concrete structure (RCC)96%92%
Units booked70%66%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Anika Piccadilly is a project by Arun Pitamber Sheth in Punawale, Pune 411033, registered with MahaRERA as 2 phases (P52100049940, P52100078875). The first phase was launched in March 2023. Together the phases have 408 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 96% complete and final finishes 45% complete. 1 of the 2 phases have their structure complete.

285 of the 408 units reported for sale are booked (70%). In 2026 registered sales, 80% of flats here sold at ₹8,400 per sq ft or less (up 9% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 20% lower than the typical Punawale rate in 2026. Most buyers paid ₹60–67 lakh for 2 BHK flats of about 800 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100049940 and P52100078875.Open MahaRERA and search P52100049940All projects in Tathawade, Punawale, Jambhe