VTP Monarque Phase 1, Hinjewadi

by Mexus Real Estate Developers LLP. Hinjewadi, Pune 411057. View on Google Maps

Launched
5 years 4 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
285 of 50457% booked
Price per sq ft (incl. balconies and terrace)
₹11,9002026 so far · 41 salesup 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK216
3 BHK216
4 BHK72
Total units504
Buildings2
Land4.8 acres
Complaints on MahaRERA (filed by or against the builder)3

Since Dec 2025: booked 246 → 285 · complaints 0 → 3

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
780 – 860 sq ft₹90 lakh – ₹1.01 crore
950 sq ft₹1.12 – 1.16 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,200 per sq ft65 sales
2025up 5% on 2024₹11,800 per sq ft111 sales
2026 so farup 1% on 2025₹11,900 per sq ft41 sales

Rate vs other Hinjewadi projects, 2026: similar

Compared with 6 similar projects in PIN 411057

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 4 mths4 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2029July 2029
Concrete structure (RCC) complete0%18%
Share of units booked57%64%
Complaints on MahaRERA (filed by or against the builder)32

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 2 months of the promised 5 years 4 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 65%Jul 2026: Excavation 65%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 65%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
65%0%0%285
65%0%0%246
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

VTP Monarque Phase 1 (MahaRERA P52100077322) is a residential project by Mexus Real Estate Developers LLP in Hinjewadi, Pune 411057. It was launched in August 2024. It has 504 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation 65% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

285 of its 504 units are booked (57%). Since the December 2025 update, 39 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹11,900 per sq ft or less (up 1% on 2025), counting balconies and terrace in the size, based on 41 registered sales. Buyers here paid a rate similar to other Hinjewadi projects in 2026. Most buyers paid ₹90 lakh–₹1.01 crore for flats of 780–860 sq ft and ₹1.12–1.16 crore for 950 sq ft.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077322.Check it on MahaRERA (P52100077322)All projects in Wakad, Hinjewadi, Marunji