Yashwin Urbo Centro Phase 2, Wakad

by Vilas Javdekar Infinitee Developers Pvt. Ltd.. Wakad, Pune 411057. View on Google Maps

Launched
4 years 8 months promised
Possession date (MahaRERA)
2 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
17%Mid-constructionAverage across 4 buildings
Units booked
1,002 of 1,03996% booked
Price per sq ft (incl. balconies and terrace)
₹11,4002026 so far · 32 salesup 5% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK426
3 BHK567
4 BHK6
Other units (shops, offices or not given by type)40
Total units1,039
Buildings4
Land3.1 acres
Complaints on MahaRERA (filed by or against the builder)3

Since Dec 2025: booked 938 → 1,002 · structure 6% → 17% · complaints 2 → 3

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
960 – 1,140 sq ft₹1.08 – 1.27 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,500 per sq ft182 sales
2025up 4% on 2024₹10,900 per sq ft724 sales
2026 so farup 5% on 2025₹11,400 per sq ft32 sales

Rate vs other Wakad projects, 2026: similar

Compared with 6 similar projects in PIN 411057

Projects with 450–2,000 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 8 mths5 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2029December 2029
Concrete structure (RCC) complete17%0%
Share of units booked96%64%
Complaints on MahaRERA (filed by or against the builder)33

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years of the promised 4 years 8 months have passed
Concrete structure (RCC) 17% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 33%Jun 2025: Excavation 33%Dec 2025: Excavation 98%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 6%Jul 2026: Concrete structure (RCC) 17%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 17%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%17%0%1,002
98%6%0%938
33%0%0%157

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Yashwin Urbo Centro Phase 2 (MahaRERA P52100077674) is a residential project by Vilas Javdekar Infinitee Developers Pvt. Ltd. in Wakad, Pune 411057. It was launched in October 2024. It has 1,039 units in 4 buildings: 999 homes (2, 3 & 4 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 17% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

1,002 of its 1,039 units are booked (96%). Since the December 2025 update, 64 more units have been booked and the reported concrete structure (RCC) has gone from 6% to 17%. 80% of the 2026 (so far) sales we found here were at ₹11,400 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size, based on 32 registered sales. Buyers here paid a rate similar to other Wakad projects in 2026. Most buyers paid ₹1.08–1.27 crore for flats of 960–1,140 sq ft.

Vilas Javdekar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA45
Completed without extending the possession date25
Completed after an extension, or lapsed1
Under construction19
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all Vilas Javdekar projects27 (19 of 45 projects)

See all Vilas Javdekar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.