Skip to main content
← Back

Construction of 24 LIG, 768 MIG and commercial building on S.No. 126 127/1 Tathawade, Pune. Phase-II

by Pune Housing & Area Development Board. Tathawade, Pune 411033. View on Google Maps

Launched
1 year 11 months originally promised
Possession date (MahaRERA)
2 years 2 months awayExtended by 2 years (originally December 2026). Why possession dates change
Concrete structure (RCC)
96%Mid-constructionAverage across 4 buildings
Units booked
Bookings not reported

Project facts

1 BHK22
2 BHK770
Other units (shops, offices or not given by type)596
Total units1,388
Buildings4
Land5.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 24% → 96% · final finishes 0% → 23% · possession date December 2026 → December 2028 · total units 1,415 → 1,388

Share on WhatsApp

Compared with 6 similar projects in PIN 411033

Projects with 350–1,600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 11 mths4 yrs 6 mths
Possession date extendedBy 2 years1 of 6
Possession date (MahaRERA)December 2028September 2029
Concrete structure (RCC) complete96%7%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 9 months of the originally promised 1 year 11 months have passed
Concrete structure (RCC) 96% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 24%Jun 2025: Concrete structure (RCC) 24%Dec 2025: Concrete structure (RCC) 24%Jul 2026: Concrete structure (RCC) 96%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 23%Excavation 100%Concrete structure (RCC) 96%Final finishes 23%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%96%23%—
100%24%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Construction of 24 LIG, 768 MIG and commercial building on S.No. 126 127/1 Tathawade, Pune. Phase-II (MahaRERA P52100078654) is a residential project by Pune Housing & Area Development Board in Tathawade, Pune 411033. It was launched in January 2025. It has 1,388 units in 4 buildings: 792 homes (1 & 2 BHK) and 596 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 2 years from the original December 2026. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 96% complete, final finishes 23% complete. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 24% to 96% and the possession date has moved from December 2026 to December 2028.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078654.Check it on MahaRERA (P52100078654)All projects in Tathawade, Punawale, Jambhe